15th December 07

Well finally our busy week is nearly over, on Friday 14th, the guys managed to finish tackwelding FR 12 and F13 to the hull floor. Also the stiffeners on FR 1-3 lower sections were fitted having been sitting there for a week waiting to get fitted.

Today Saturday, I managed to finish the last big frame, No 14. (below)



Side stringers laid into approx positions. Bottom Stringers (longitudionals ) all in there correct place and level to the floor. We did have a major kink to work around on the LSH where the sheets are joined. The centre beam ahead of the last frame is also fitted to allow FR 14 to get placed.